The whole project is fully sold

14 sea-view villas, fully sold and currently under construction. A transparent look at how a commercial concept becomes a real built project.

14Villas
SOLD OUTStatus
22 Oct 2026Last update
Dec. 2026Estimated delivery

The project

  • 14 sea-view villas, fully sold.
  • Construction underway with regular photographic updates.
  • Aurea is a real reference for product, execution and positioning across future projects.

Current project status

Photographic update dated 22 October 2026. The latest technical percentages available are still those from the 21 September report; this new update shows the current visual state of the works without assigning a new overall percentage.

Last update
22 Oct 2026
Façades
Advanced
Interiors
In progress
Finishes
In progress
Type A structure
Completed according to the 21 Sep report.
Type B & C structure
Type B is nearly complete; Type C remains in the structural phase.
Architecture
Progressing in Type A, started in Type B and no progress reported yet in Type C.
Technical installations
Underway in Type A and started in Type B; no progress reported yet in Type C.
Pools
Type A: 90% · Type B: 64.04% · Type C: 25.14%.

Construction updates

We track execution through periodic site reports and a curated selection of key images, showing both the overall build and progress by villa type.

22 Oct 2026
Construction update: advanced façades and finishing works underway
FaçadesInteriorsTimberFinishes

The 22 October photographic update shows a visible step forward from the previous report. Several villas now have clearly defined exterior volumes and advanced façades, while timber ceilings, interior finishes, technical installations and finishing works continue to progress. The images also show simultaneous activity across several units.

This is a photographic update and does not include a new technical percentage report. No new overall project percentage is therefore assigned; the latest published percentages remain those from the 21 September update.
21 Sep 2026
Construction update: Type A exceeds 65% as interior works, technical installations and pools progress
StructureArchitectureTechnical installationsPools

The weekly report through 21 Sep places total reported progress at 65.43% for Type A villas, 51.75% for Type B and 34.88% for Type C. Type A structure is complete, with interior works, technical installations and initial finishes continuing; its pool is at 90%. Type B structure is nearly complete, with interior works and technical installations started and the pool at 64.04%. Type C remains mainly in the structural phase, with its pool at 25.14%.

Type A65.43%
Type B51.75%
Type C34.88%
Percentages correspond to total reported progress for each villa type in the weekly report through 21 Sep; they do not represent a single overall project percentage.
04 Sep 2026
Construction update: execution moves into interior works, technical installations and initial finishes
StructureArchitectureTechnical installationsFinishes

The weekly report through 04 Sep shows a clear transition in the build. The most advanced units now combine structure, interior works, technical installations and initial finishing works. Type A structure is reported as complete, Type B is nearly complete and Type D continues to develop. The new images show the internal routes, increasingly defined volumes and simultaneous progress across several work fronts.

Type A60.99%
Type B49.73%
Type D27.58%
Percentages correspond to the total reported progress for each villa type in the weekly report through 04 Sep; they do not represent one overall project percentage.
28 Jul 2026
Construction update: more structured units and strong retaining-wall progress
Structure Retaining walls Active works

New construction update for Aurea Villas. This stage shows clear progress across the upper units, with several structural volumes now well defined, while the retaining walls and lower terraces have also advanced significantly. The new images give a much clearer view of the project layout and how the overall development is taking shape.

13 Jul 2026
Construction update: structural progress and new active work fronts
Structure Slabs Active works

New construction update for Aurea Villas. The structural progress is clearly visible, with several modules already advancing on the upper levels, new columns and slabs underway, and continued works across the lower block. The aerial photos show the evolution of the site, internal access areas and the pace of execution across several active work fronts.

25 May 2026
New progress: more units advancing in structure and a wider construction front
Structure Foundations Retaining works

The site continues to gain momentum: several units are now clearly progressing in structure, while foundation, retaining and lower-block works continue. The new aerial views show a visible evolution of the overall development and the project access areas.

01 Apr 2026
Structure update: formwork and first slabs underway
Structure Formwork Concrete

Progress is visible on the main block: formwork assembled and pours being prepared, while works continue across access areas and sea-view units.

13 Feb 2026
Structure progressing: columns rising & foundations advancing
Foundations Columns Structure

Visible progress across multiple units: several columns already cast and other areas in rebar/formwork preparation. Foundation works continue while the next structural cycle is prepared.

05 Feb 2026
Earthworks, retaining walls and early structure
Foundation Walls Structure

Main platform set, retaining walls executed and rebar works started for columns/footings across the plot. Next milestone: formwork and concrete pour for structural elements.